## Building permits

- Alteration, filed Sep 27, 2023, estimated cost $1K, described as “Installation of temporary heavy duty sidewalk shed as per plans. No change in use, egress or occupancy. Sidewalk shed shall comply with chapter #33 of 2022 the NYC building code. Live load 300PSF.”
- Alteration, filed Jun 28, 2023, estimated cost $8K, described as “Modification to existing sprinkler and standpipe fire department connections and associated piping. No change to use, egress or occupancy.”
- Alteration, filed Nov 23, 2022, estimated cost $20K, described as “Minor Renovation includes but not limited to, New Partitions, Lighting”

## Property taxes

- Assessment: $2,384,100
- 2026–27 tax: $245,964
- Market value (city estimate): $5,298,000
- Taxable value: $2,267,370
- Assessed land: $63,000
- Assessed improvements: $2,321,100

## Zoning

R6: floor area ratio 4.45 built, above the 2.43 base zoning allows, which bonuses, transfers or older rules can permit.

## Flood zone

Current FEMA flood map: zone X, minimal flood hazard.

## Board and land use applications

- Roundtable Senior Center (City Planning 2021K0328): City property acquisition, Completed, decided May 25, 2022. A lease-renewal \[PQ\] to facilitate the continued use of a five-story senior center, \[total approx. 47,000 sf\], is being sought by DFTA and DCAS at 1175 Gates Avenue in Bushwick, Community District 4, Brooklyn.
- LSSMNY Early Life Center 9 (continued use) (City Planning P2015K0149): Completed, decided Feb 25, 2016. Application for an acquisition of an existing facility to provide continued use of the LSSMNY Early Life Center 9, a child care and senior center, at 1175 Gates Avenue in CD 4, Brooklyn.
- ROUNDTABLE DCC & SENIOR CENTER (City Planning P1992K0186): Completed, decided Dec 22, 1992. ACQUISITION OF A 5-STORY BLDG TO CONTINUE TO OPERATE A DAY\*CARE & SENIOR CENTER TO SERVE APPX 160 CHILDREN & 20 SENIORS\*IN THE BUSHWICK II URA
- Bushwick Neighborhood Plan (City Planning 2019K0199): Completed. This is an application for a 300-block section of Bushwick, Brooklyn, Community District 4 to create a thriving and inclusive Bushwick through preservation and creation of affordable housing, targeted investments in neighborhood…