805 Rockaway Avenue, Brooklyn
Condominium · 174 units · built c. 1930 · Block 3603, Lot 7501.
Building permits
- Alteration, filed Apr 17, 2026, estimated cost $15K, described as “Interior renovation of commercial space to install new FAMACT and adult care center, etc. No change of use, egress or occupancy.”
- Alteration, filed Feb 14, 2025, estimated cost $1K, described as “It is proposed to install a curb cut as shown on plans. No change to use, egress or occupancy under this application.”
- Alteration, filed Feb 21, 2024, described as “Installation of temporary supported scaffold per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.”
- Alteration, filed Jan 3, 2024, described as “Installation of temporary heavy duty sidewalk shed per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.”
- Alteration, filed Jul 9, 2023, estimated cost $50K, described as “Extension of existing sprinkler system piping to add sprinkler heads in prefabricated paint spray booth with no heat, & sp heads in fire proof spray room enclosure and duct work for fire suppression compliance..”
- Alteration, filed Jun 12, 2023, described as “Installation of temporary supported scaffold for hoist landing platform per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.”
- Alteration, filed Apr 27, 2023, estimated cost $3K, described as “Installation of a temporary needle beam per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application”
- Alteration, filed Apr 18, 2023, estimated cost $120K, described as “Assembly and installation of prefabricated paint spray booth on 001 with no heat and duct work from 001 to 007 then thru to roof for exhaust for commercial use.”
- Alteration, filed Mar 14, 2023, estimated cost $1K, described as “Suspended Hanging Scaffold Installation as per plans filed herewith. No change in use, egress or occupancy”
- Alteration, filed Jan 13, 2023, described as “Installation of temporary construction fence per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.”
- Alteration, filed Dec 29, 2022, estimated cost $25K, described as “West Hoist/Rockaway Wing - Installation of 6,000# AVRO SC270GZ Temporary single car personnel/material hoist per plan and application submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or…”
- Alteration, filed Dec 29, 2022, estimated cost $25K, described as “East Hoist/ Thatford Wing - Installation of 6,200# Alimak 28/37 TD temporary single car personnel/material hoist per plan and application submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or…”
- Alteration, filed Nov 8, 2022, estimated cost $15K, described as “Installation of pipe scaffolding as per plans during construction. No change in use, egress or occupancy. Pipe scaffolding shall comply with chapter 33 of NYC building code of 2014.”
- Alteration, filed Oct 25, 2022, described as “Installation of temporary heavy duty sidewalk shed per plan submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress and/or occupancy with this application.”
- Alteration, filed Dec 29, 2021, estimated cost $10K, described as “Installation of shoring post under roof beam”
- Alteration, filed Nov 16, 2021, estimated cost $5K, described as “Installation of construction fence as per drawing.”
- Alteration, filed Nov 4, 2021, estimated cost $40K, described as “Erect 750 lf of 8' high wood construction fence to enclose site.”
- Alteration, filed Jul 13, 2021, estimated cost $1K, described as “It is proposed to file for plumbing work in-conjunction with new building appl 321599212”
- Alteration, filed Apr 28, 2021, estimated cost $1K, described as “It is proposed to file for mechanical work filed in conjunction with NB appl. 321599212.”
- Alteration, filed Apr 28, 2021, estimated cost $1K, described as “It is proposed to file for structural work filed in conjunction with NB application 321599212 as shown on plans.”
- Alteration, filed Mar 31, 2021, estimated cost $1.6M, described as “It is proposed to file for sprinkler and standpipe work filed in conjunction with NB appl. 321599212.”
- Alteration, filed Mar 31, 2021, estimated cost $500K, described as “It is proposed to install new boilers as shown on plans, no change to use, egress or occupancy.”
Property taxes
- Assessment
- $15,103,801
- Market value (city estimate)
- $33,564,000
- Taxable value
- $0
- Assessed land
- $517,501
- Assessed improvements
- $14,586,300
- Condo units with their own tax lots
- 4
Tax breaks
- IDA PILOT, with no end date.
- 420-c exemption, through Jun 30, 2062, about $1,428,189 a year below the full tax.
Zoning
M1-4/R6A (part of the lot is M1-4/R7A): floor area ratio 3.47 built, above the 3.00 base zoning allows, which bonuses, transfers or older rules can permit.
Flood zone
Current FEMA flood map: zone X, minimal flood hazard.
In the news
Pols Kick Off Construction of Affordable Housing and Light Manufacturing Complex in Brownsville, Brownstoner, May 19, 2022.