# 1407 Linden Boulevard, Brooklyn

Co-op · 423 units · built 1958 · Block 3634, Lot 1.

On Umarelli: https://umarelli.org/nyc/3036340001/1407-linden-boulevard

More construction in Brownsville: https://umarelli.org/nyc/brooklyn/brownsville.md

Every lot on block 3634: https://umarelli.org/nyc/brooklyn/3634.md

## Building permits

- Alteration, filed Oct 30, 2026, estimated cost $329K, described as “Amend Certificate of Occupancy to add 18 parking spaces in existing open space for a new Open Parking Lot, accessory to adjacent building 1407 Linden Blvd.”
- Alteration, filed Oct 23, 2026, estimated cost $49K, described as “Filing for Facade Restoration work. No Change to Use, Egress or Occupancy.”
- Alteration, filed Oct 23, 2026, estimated cost $40K, described as “Filing for Facade Restoration work. No Change to Use, Egress of Occupancy”
- Alteration, filed Oct 23, 2026, estimated cost $43K, described as “Filing for Facade Restoration work. No Change to Use, Egress or Occupancy.”
- Alteration, filed Sep 28, 2026, estimated cost $877K, described as “Herewith filing to alter the roof of this existing garage to be roof top parking for this parking facility and adding ramps. Change to use.”
- Alteration, filed Feb 24, 2026, described as “Gas material hoist during roof replacement”
- Alteration, filed Jan 14, 2026, described as “Material hoist. Materials only. No work from hoist.”
- Alteration, filed Oct 29, 2025, estimated cost $291K, described as “Filing for Lobby Renovations, Exterior Pergola and PA Community Room Renovation. No change to Use, Egress of Occupancy.”
- Alteration, filed Oct 24, 2025, estimated cost $793K, described as “Herewith filing for repairs to this existing garage. No change to use, egress or occupancy.”
- Alteration, filed Oct 23, 2025, estimated cost $6.3M, described as “Installing 6 domestic hot water heat pumps, 11 hot water storage tanks, new dom water serv,., replacement of wc, repl of W/S piping in basement, installing two electric swing tanks and domestic pumps as per plans filed herewith”
- Alteration, filed Oct 23, 2025, estimated cost $870K, described as “Filing for Exterior Campus Perimeter fencing and Campus walkway fencing, Playground & sports court Renovation. No change to Use, Egress or Occupancy.”
- Alteration, filed Oct 23, 2025, estimated cost $2.2M, described as “Replacing existing water closets throughout entire and domestic water piping in basement as per plans filed herewith.”
- Alteration, filed Oct 23, 2025, estimated cost $158K, described as “Filing for Renovations to Lobby and Exterior Pergola. No change to Use, Egress or Occupancy.”
- Alteration, filed Oct 23, 2025, estimated cost $2.0M, described as “Replacing existing domestic water/sanitary risers from basement to 14th floor and domestic header on 14th floor as per plans filed herewith.”
- Alteration, filed Oct 23, 2025, estimated cost $2.2M, described as “Replacing existing water closets throughout entire and domestic water piping in basement as per plans filed herewith.”
- Alteration, filed Oct 23, 2025, estimated cost $1.9M, described as “Replacing existing domestic water/sanitary risers from basement to 14th floor and domestic header on 14th floor as per plans filed herewith.”
- Alteration, filed Oct 23, 2025, estimated cost $366K, described as “Filing for Lobby Renovations, Exterior Pergola, Doctors Office Whitebox, and Exterior Ramp Replacement. No change to Use, Egress or Occupancy.”
- Alteration, filed Oct 23, 2025, estimated cost $2.7M, described as “Replacing existing domestic w/s risers from basement to 14th floor and domestic header on 14th floor as per plans filed herewith.”
- Alteration, filed Mar 7, 2025, estimated cost $8K, described as “Construction equipment- sidewalk- shed proposed installation of heavy duty sidewalk shed. No change in use occupancy or egress under this application, live load 300 # per square feet. Sidewalk shed shall comply with chapter #33 of the 2022…”
- Alteration, filed Nov 12, 2024, estimated cost $20K, described as “Alteration type 3 - construction equipment - sidewalk- shed proposed installation of heavy duty sidewalk shed. No change in use occupancy or egress under this application. Live load 300 per square feet. Sidewalk shed shall comply with…”
- Alteration, filed Jul 29, 2024, described as “Outrigger suspended scaffolding during facade repair work”
- Alteration, filed Jul 29, 2024, described as “Outrigger suspended scaffolding during facade repair work”
- Alteration, filed Jul 26, 2024, described as “Outrigger suspended scaffolding during facade restoration work”
- Alteration, filed May 6, 2024, estimated cost $150K, described as “Filing for water tank enclosure shoring & repairs. Work to include roof protection, removal of perimeter brick enclosure wall & concrete framing elements, construction of a new parapet wall at water tank roof level. No change to use,…”
- Alteration, filed Feb 20, 2024, estimated cost $7K, described as “Install supported pipescaffold as per drawings.”

6 more, older permits are in this building’s full list on the map: https://umarelli.org/nyc/3036340001/1407-linden-boulevard.

## Property taxes

- Assessment: $13,342,950
- 2026–27 tax: $186,543
- Market value (city estimate): $29,651,000
- Taxable value: $0
- Assessed land: $1,008,000
- Assessed improvements: $12,334,950

## Tax breaks

- Redevelopment company exemption, with no end date, about $1,659,730 a year below the full tax.
- J-51 abatement, through Dec 31, 2043, a $33,790 credit this tax year.

## Zoning

R6: floor area ratio 2.26 built, 2.43 allowed by base zoning.

## Flood zone

Current FEMA flood map: zone X, minimal flood hazard.

From New York City and Jersey City public records, refreshed within a day of each release. Sources: https://umarelli.org/sources. Methodology and corrections: https://umarelli.org/methodology