265 Forbell Street, Brooklyn
Public school · built 1971 · Block 4243, Lot 1.
Building permits
- Alteration, filed May 30, 2024, estimated cost $20K, described as “Fn/PS214K - for temporary construction equipment submitting on behalf of contractor, related with DOB job # B00998035. No change in use, occupancy or egress”
- Alteration, filed Mar 15, 2024, estimated cost $100K, described as “Filing herewith for the installation of temporary steel frame to shore stone column for repair.”
- Alteration, filed Sep 27, 2022, estimated cost $17K, described as “Filing for support of excavation in the school yard. No change in use, egress or occupancy.”
- Alteration, filed Aug 19, 2022, estimated cost $25K, described as “Filing for amendment for approved drawing adding additional plywood fence.”
- Alteration, filed Oct 21, 2021, estimated cost $100K, described as “Installation of temporary construction equipment as indicated on plans. No change in use, egress or occupancy”
- Alteration, filed Sep 9, 2021, estimated cost $50K, described as “Installation of temporary construction equipment,fence, as indicated on plans. No change in use, egress or occupancy”
- Alteration, filed Jun 14, 2021, estimated cost $3.1M, described as “Filing herewith for accessibility upgrade for the existing building and addition of elevator and accessibility lift.”
- Alteration, filed Jun 14, 2021, estimated cost $176K, described as “Filing herewith for the mechanical work related to the accessibility upgrade of the existing space.”
- Alteration, filed Jun 14, 2021, estimated cost $339K, described as “Filing herewith for Plumbing infrastructure renovations and additions as required for toilet rooms, drinking fountains, roof drains and associated pipings.”
- Alteration, filed Jun 11, 2021, estimated cost $84K, described as “Installation of stormwater management system (subsurface retention) per dep on-site public property green infrastructure retrofit contract, no change to use, egress or occupancy.”
- Alteration, filed Jun 11, 2021, estimated cost $10K, described as “Plumbing work associated with the installation of stormwater management system (subsurface retention) per dep on-site public property green infrastructure retrofit contract, no change to use, egress or occupancy.”
Property taxes
- Assessment
- $7,353,000
- Market value (city estimate)
- $16,340,000
- Taxable value
- $0
- Assessed land
- $936,000
- Assessed improvements
- $6,417,000
Zoning
R4: floor area ratio 0.81 built, 1.00 allowed by base zoning.
Flood zone
Current FEMA flood map: zone X, minimal flood hazard.