374 Wortman Avenue, Brooklyn
Public School · built 1963 · Block 4401, Lot 1.
Building permits
- Alteration, filed Jun 11, 2026, estimated cost $1.4M, described as “Jerome Playground reconstruction to install storm water system only on site. All as per plans filed herewith.”
- Alteration, filed Nov 13, 2025, estimated cost $270K, described as “Installation of Supplemental Cooling Split AC System in 1st Floor Auditorium.”
- Alteration, filed Feb 28, 2024, estimated cost $10K, described as “Support of excavation for new new ramp & elevator shaft installation”
- Alteration, filed Oct 13, 2023, estimated cost $10K, described as “Installation of supported scaffold for work location access”
- Alteration, filed Oct 10, 2023, estimated cost $10K, described as “Installation of sidewalk shed for public protection during cinstruction work”
- Alteration, filed Oct 10, 2023, estimated cost $20K, described as “Installation of construction fence for public protection from areas of construction work”
- Alteration, filed Aug 21, 2023, estimated cost $97K, described as “PL work correspondent to installation of a new water line and RPZ within a existing comfort station @Jerome Playground Comfort Station. All as per plans filed herewith”
- Alteration, filed May 25, 2022, estimated cost $5.8M, described as “Construction of an elevator bulkhead, elevator and elevator shaft; selective demolition and improvements within the existing building, including general construction work, interior finish work; and site improvement work.”
Property taxes
- Assessment
- $5,860,800
- Market value (city estimate)
- $13,024,000
- Taxable value
- $0
- Assessed land
- $873,000
- Assessed improvements
- $4,987,800
Zoning
R5: floor area ratio 0.58 built, 1.50 allowed by base zoning.
Flood zone
Current FEMA flood map: zone X, minimal flood hazard.