36-14 12th Street, Queens
Religious · built 1950 · Block 352, Lot 1.
Building permits
- Alteration, filed Jun 27, 2025, estimated cost $50K, described as “Replacement of 2 indoor vertical ACs. No change in egress, use or occupancy.”
- Alteration, filed Feb 11, 2025, estimated cost $45K, described as “Proposed installation of 3 heat pump system with 12 fan coil units.”
- Alteration, filed Apr 4, 2024, estimated cost $1K, described as “Installation of temporary heavy duty sidewalk shed as per plans. No change in use, egress or occupancy. Sidewalk shed shall comply with chapter #33 of 2022 the NYC building code. Live load 300PSF.”
- Alteration, filed Mar 27, 2024, estimated cost $103K, described as “Installation of new rooftop fence as indicated on drawings.”
- Alteration, filed Mar 26, 2024, estimated cost $1.5M, described as “Facade and roof restoration as indicated on drawings.”
- Alteration, filed Aug 16, 2023, estimated cost $50K, described as “Renovation of interior stair and doorway at Northwest corner of building. New shaft wall, concrete floor and new doors. No change in egress, use or occupancy.”
- Alteration, filed Aug 15, 2023, estimated cost $30K, described as “Excavate and remove soil from the side open yard to install new walkway.”
- Alteration, filed Aug 14, 2023, estimated cost $7K, described as “Construction fence on the ground inside the property to close the construction area.”
- No Work, filed Jun 15, 2023
- Alteration, filed May 18, 2023, estimated cost $100K, described as “Interior non-structural demolition and installation of partitions at DiMarco Building. Two new exterior doors. New ADA ramp in courtyard. No change in egress, use or occupancy.”
- Alteration, filed Sep 24, 2021, estimated cost $407K, described as “Facade and roof repairwork as per plans filed herewith. No change to use, egress or occupancy.”
- Alteration, filed Sep 14, 2021, estimated cost $1K, described as “Installation of temporary heavy duty sidewalk shed as per plans. No change in use, egress or occupancy. Sidewalk shed shall comply with chapter #33 of the NYC building code. Live load 300PSF.”
- Alteration, filed Apr 29, 2021, estimated cost $92K, described as “Replace boiler and oil burner.”
Property taxes
- Assessment
- $6,755,400
- Market value (city estimate)
- $15,012,000
- Taxable value
- $0
- Assessed land
- $1,278,900
- Assessed improvements
- $5,476,500
Tax breaks
- Nonprofit exemption (house of worship), with no end date, about $732,826 a year below the full tax.
Zoning
R5D: floor area ratio 0.58 built, 2.00 allowed by base zoning.
Flood zone
Current FEMA flood map: zone X, minimal flood hazard.
Board and land use applications
- HOUR CHILDREN (City Planning P2010Q0097): Completed, decided Oct 1, 2010. Proposed rezoning from M1-1 to R5D/C1-3 to facilitate a 4-story supportive housing development.
- JOSEPH DIMARCO DCC (City Planning P1992Q0335): Completed, decided Dec 27, 1993. ACQUISITION OF A 2-STORY BLDG TO CONTINUE TO OPERATE A DAY*CARE CENTER TO SERVE APPX 190 CHILDREN