37-10 10th Street, Queens
Hotel · built 2019 · Block 359, Lot 21.
Building permits
- Alteration, filed Nov 15, 2024, estimated cost $5K, described as “Filing to register (2) laars boilers model #RHCV2000. Boilers incorrectly filed as hwh under 421643920. All gas piping and equipment filed and signed off under 421643920-02. Comply with ecb violations 39125080L and 39125079Y.”
- No Work, filed Sep 1, 2021
- Alteration, filed Feb 25, 2020, estimated cost $90K, described as “Alteration type 3 - construction equipment - scaffold proposed installation of pipe scaffold for new building as per plans. No change in use occupancy or egress under this application.”
- Alteration, filed Feb 25, 2020, estimated cost $50K, described as “Installation of temporary heavy duty sidewalk shed as per plans. No change in use, egress or occupancy.sidewalk shed shall comply with chapter #33 of the NYC building code.live load 300PSF.”
- Alteration, filed Aug 14, 2019, estimated cost $5K, described as “Proposed installation of heavy duty sidewalk shed as per plans. Live load 300 lbs per square feet. Sidewalk shed shall comply with chapter #33 of the NYC building code. No change in use, occupancy, or egress under this application.”
- Alteration, filed Jul 30, 2019, estimated cost $1K, described as “Hereby filing for new curb cut for new building”
- Alteration, filed Jul 30, 2019, estimated cost $1K, described as “Hereby filing for new curb cut on 10 street (15'-0")”
- Alteration, filed Jul 29, 2019, estimated cost $1K, described as “Hereby filing for new curb cut on 37TH street”
- Alteration, filed May 17, 2019, estimated cost $5K, described as “Install temporary construction fence as per plan filed herewith in conjunction with NB #421643920.”
- Alteration, filed May 10, 2019, estimated cost $8K, described as “Proposed installation of temporary pipe scaffold for new building as per plans. Work shall comply with chapter #33 of the NYC building code. No change in use, occupancy, or egress under this application.”
- Alteration, filed Mar 6, 2019, estimated cost $1K, described as “Installation of temporary heavy duty sidewalk shed as per plans. No change in use, egress or occupancy.sidewalk shed shall comply with chapter #33 of the NYC building code.live load 300PSF.”
- Alteration, filed Sep 11, 2018, estimated cost $1K, described as “Filing herewith for installation of Temporary Construction Fence in conjunction with NB 421643920”
- Alteration, filed May 23, 2018, estimated cost $1K, described as “Temporary 8' construction fence”
- Alteration, filed May 22, 2018, estimated cost $1K, described as “Installation of temporary heavy duty sidewalk shed as per plans. No change in use, egress or occupancy.sidewalk shed shall comply with chapter #33 of the NYC building code.live load 300PSF.”
Property taxes
- Assessment
- $17,250,750
- 2026–27 tax
- $290,366
- Market value (city estimate)
- $38,335,000
- Taxable value
- $15,053,220
- Assessed land
- $540,000
- Assessed improvements
- $16,710,750
Tax breaks
- ICAP abatement, through Jun 30, 2047, a $1,342,607 credit this tax year.
Zoning
M1-3: floor area ratio 5.67 built, above the 5.00 base zoning allows, which bonuses, transfers or older rules can permit.
Flood zone
Current FEMA flood map: zone X, minimal flood hazard.
Recent sales
- May 16, 2023: $76,500,000
- Jul 18, 2018: $11,500,000
Open-market sales since 2016, from the Department of Finance’s sales files.
Board and land use applications
- Extension to finish construction (Board of Standards and Appeals 2021-74-BZY): Extension to finish construction, Withdrawn, filed Nov 17, 2021, decided Dec 28, 2021. Extension of time (§11-332) to complete construction of a minor development commenced under the prior zoning. M1-3 zoning district.