Building permits
- New Building, filed Feb 25, 2026, 1 story, described as “New building filed herewith as per plans”
- Alteration, filed Sep 17, 2026, estimated cost $40K, described as “Architectural work for temp trailer filed herewith. Trailer(s) is temporary in nature and shall be removed upon completion of construction activities.”
- Alteration, filed Jul 9, 2026, estimated cost $224K, described as “Installation of pre-fabricated platform. No change in use, egress, or occupancy.”
- Alteration, filed Mar 9, 2026, estimated cost $14K, described as “Alteration to boiler room makeup air system. No change in use, egress, or occupancy. Jamaica Training Center.”
- Alteration, filed Dec 22, 2025, estimated cost $600K, described as “General construction for the installation of EV charging stations, including conduit runs, foundations, bollards, and associated site work, as per drawings filed herewith.”
- Alteration, filed Nov 12, 2025, estimated cost $37K, described as “Installation of protective wire fence and bollards for exterior sprinkler system RPZ.”
- Alteration, filed Oct 27, 2025, estimated cost $70K, described as “Application filed interior/exterior renovation on partial 1ST floor and roof as per plans filed herewith. No change in use, egress or occupancy.”
- Alteration, filed Jul 7, 2025, estimated cost $26K, described as “Installation of a new dedicated fire sprinkler water main; replacement and relocation of an existing electric water heater.”
- Alteration, filed Jan 23, 2025, estimated cost $313K, described as “Filing herewith for the installation of a new wet sprinkler system. No change in use, egress, or occupancy. PAA filed to reflect field conditions.”
- Alteration, filed Apr 28, 2022, estimated cost $138K, described as “Interior bathroom renovation”
- Alteration, filed Apr 6, 2022, estimated cost $138K, described as “Interior bathroom renovation”
- Alteration, filed Mar 23, 2022, estimated cost $310K, described as “Interior bathroom renovation”
- Alteration, filed Nov 3, 2021
- Alteration, filed Nov 3, 2021
- Alteration, filed Oct 14, 2021, estimated cost $44K, described as “New Electric Vehicle Charging Station”
- Alteration, filed Aug 27, 2021, estimated cost $30K, described as “Installation of HVAC system on first floor and roof. No change in use, egress, or occupancy group.”
- Alteration, filed Feb 16, 2021, estimated cost $60K, described as “Install (3) outdoor condensers on roof and (8) indoor units on first floor.”
Zoning
M1-1: floor area ratio 0.00 built, 1.00 allowed by base zoning.
Flood zone
Current FEMA flood map: zone X, minimal flood hazard.