159-30 Rockaway Boulevard, Queens
Commercial · built 1998 · Block 14260, Lot 90.
Building permits
- No Work, filed Nov 2, 2026
- Alteration, filed Oct 30, 2026, estimated cost $450K, described as “Installation of interior non-bearing partitions & related finishes. No change in use & egress. Change in occupancy: maximum occupant load in cel increased from 116 to 300 persons. Maximum occupant load on floor 01 decreased from 510 to 437…”
- Alteration, filed Oct 20, 2026, estimated cost $30K, described as “Structural work for coring existing slabs for MEP conduits & pipes for C3 tenant buildout”
- Alteration, filed Oct 16, 2026, estimated cost $150K, described as “General construction for C1 tenant buildout.”
- Alteration, filed Oct 16, 2026, estimated cost $500K, described as “General construction for C3 tenant buildout.”
- Alteration, filed Oct 16, 2026, estimated cost $600K, described as “General construction for C2 tenant buildout.”
- Alteration, filed Oct 15, 2026, estimated cost $70K, described as “Sprinkler work for C3 tenant buildout”
- Alteration, filed Oct 15, 2026, estimated cost $25K, described as “Plumbing work for C3 tenant buildout”
- Alteration, filed Oct 15, 2026, estimated cost $75K, described as “Sprinkler/Standpipe work for C2 tenant buildout”
- Alteration, filed Oct 15, 2026, estimated cost $175K, described as “Mechanical work for C3 tenant buildout”
- Alteration, filed Oct 14, 2026, estimated cost $200K, described as “Mechanical work for C2 tenant buildout”
- Alteration, filed Oct 14, 2026, estimated cost $25K, described as “Plumbing work for C2 tenant buildout”
- Alteration, filed Oct 14, 2026, estimated cost $45K, described as “Sprinkler work for C1 tenant buildout”
- Alteration, filed Oct 14, 2026, estimated cost $30K, described as “Plumbing work for C1 tenant buildout”
- Alteration, filed Oct 14, 2026, estimated cost $150K, described as “Mechanical work for C1 tenant buildout”
- Alteration, filed Oct 14, 2026, estimated cost $50K, described as “Structural work for C2 tenant builldout for coring existing slabs for MEP conduits & pipes”
- Alteration, filed Oct 13, 2026, estimated cost $5K, described as “Structural work for C1 tenant buildout for coring existing slabs for MEP conduits & pipes”
- Alteration, filed Aug 25, 2026, estimated cost $1.0M, described as “Interior demolition on cellar, 1-5”
- Alteration, filed Aug 21, 2026, estimated cost $75K, described as “Mechanical work during interior demolition”
- Alteration, filed Aug 21, 2026, estimated cost $95K, described as “Sprinkler/standpipe work during interior demolition on cellar, 1-5. Installation of temp sprinkler loop.”
- Alteration, filed Aug 21, 2026, estimated cost $60K, described as “Plumbing work for interior demolition on cellar, 1-5”
- Alteration, filed Apr 1, 2026, estimated cost $100K, described as “Structural work for capital upgrade project”
- Alteration, filed Mar 25, 2026, estimated cost $50K, described as “Sprinkler work for capital upgrade project.”
- Alteration, filed Mar 25, 2026, estimated cost $100K, described as “Plumbing work for capital upgrade project.”
- Alteration, filed Mar 25, 2026, estimated cost $3.0M, described as “Mechanical work for capital upgrade project.”
1 more, older permit is in this building’s full list on the map.
Property taxes
- Assessment
- $35,139,150
- 2026–27 Tax
- $3,541,161
- Market value (city estimate)
- $78,087,000
- Taxable value
- $32,643,450
- Assessed land
- $5,946,300
- Assessed improvements
- $29,192,850
Zoning
M1-1: floor area ratio 0.53 built, 1.00 allowed by base zoning.
Flood zone
Current FEMA flood map: zone X, minimal flood hazard.
Board and land use applications
- Greater JFK BID (City Planning P2016Q0268): Completed, decided Nov 16, 2016. Establish a BID in the industrial area outside JFK airport